Current Status

Progress status as on
01st May 2026

Villas Update

Villa Structure (Upto Terrace Floor): 953/953

Electrical Works up to Conduit: 953/953

Water Proofing: 953/953

Internal Putty: 845/953

Internal - Tiling: 920/953

External – Texture: 890/953

Plumbing Works up to External Shafts Fixing: 864/953

Internal – 1st coat Painting: 399/953

UPVC Windows: 581/953

Wooden Doors: 501/953

Villa Internal Wiring: 469/953

External Chambers

Sewage Chambers 100%

Value Chambers 100%

Electrical & Communication 100%

Rainwater Collection Pits 100%


External Chambers

Sewage Pipeline 97%

Water Supply Pipeline 94%

Storm Water Pipeline 97%

Electrical & Communication 98%