Current Status

Progress status as on
01st April 2026

Villas Update

Villa Structure (Upto Terrace Floor): 953/953

Electrical Works up to Conduit: 953/953

Water Proofing: 953/953

Internal Putty: 842/953

Internal - Tiling: 912/953

External – Texture: 887/953

External – 1st Coat Painting: 845/953

Plumbing Works up to External Shafts Fixing: 864/953

Internal – 1st coat Painting: 326/953

UPVC Windows: 534/953

Wooden Doors: 384/953

Villa Internal Wiring: 437/953

External Chambers

Sewage Chambers 100%

Value Chambers 100%

Electrical & Communication 100%

Rainwater Collection Pits 100%


External Chambers

Sewage Pipeline 95%

Water Supply Pipeline 91%

Storm Water Pipeline 95%

Electrical & Communication 97%